Project Description
The main objectives of the project are details Land Acquisition Plan and Schedule Preparation for Proposed Gas Pipeline Installment in Cox’s Bazar District under Moheshkhali-Anowara Gas Transmission Parallel Pipeline Project. As per requirement of preparation of Land Acquisition Plan (LAP) and Plot Schedule of the project, the Consultant will undertake the following major activities:
• Review of relevant policies and legal framework of Bangladesh Government;
• Preparation of land acquisition plan for the land area to be affected by the project;
• Prepare plot schedule for LAP;
• Process data and prepare digital maps of land to be acquired by the project;
• Checking / Review of 'Cha' form, 'Uma' form, Field book ('Gha' form) and Land Schedule and collection of khatians no., name & case no. if any missing along the pipeline route and filling the same from missing khatians;
• Rerouting of the pipeline route if necessary. Checking /Review of the cadastral & Mouza Maps (RS and BS) and collection of the same if missing;
• Preparation of Route in trenching clothes (at least seven sets) showing relevant installations along the route;
• Taking still picture and video of the land along the pipeline in consultation with DC offices;
• Preparation of layout plan with appropriate scale if required;
• Preparation of documents in land acquisition and requisition related activities as per Act 2017;
• Resolve of Dispute/Arbitration (if any);
• Submission of Report for DLAC ot DC and others.